27-bay Modular Transport Hub
Bus depot, operations office, driver welfare and induction centre
Specialist Passenger Solutions is the provider of passenger transport for operatives to-and-from site at EDF nuclear construction project Hinkley Point C. The service operates from park and ride facilities at Bridgwater, with operations headquartered within a purpose-built modular building delivered by TCi construction WORKS.
TCi was appointed to design and build a fully functioning office, induction and welfare facility to support operations.
The scope of works included:
- 27-bay, three-storey modular building
- Foundations
- Transportation and craneage
- Installation and fit-out
- Supply and installation of HVAC systems
- Commissioning of M&E services
- Supply and installation of FF&E
- Ground-floor reception and administration zone
- Locker rooms and changing facilities
- Canteen with kitchenette
- Induction and training room
- Main office facility
- External access stairs and escape routes
- Internal elevator with disabled access
- Accessibility and disabled facilities
- First aid room
- Secure vetting document office
- Partitioned office areas
Design, Manufacture and Installation
Pre-start works commenced with the modular units manufactured offsite ahead of the build.
Site operations began including the preparation of concrete foundations and the installation of the required utility connections. Modular installation proceeded with lifting operations provided by Select Plant Hire Ltd and Ainscough Ltd.
Over a four-day period, the 27 modular units were installed, together with two elevators and two full-height access stairways, creating the structure for the new three-storey office and welfare facility.
Fit-Out and Commissioning
Following completion of the building installation and roof sealing processes, internal fit-out works commenced on 7 February.
Joinery works were completed ahead of the installation of mechanical and electrical services, plumbing, air conditioning, alarms and data infrastructure. Flooring and carpets were then laid before the building was cleaned and furnished by TCi furniture WORKS.
The completed facility provides a modern reception area, administration space, induction and training facilities, welfare amenities and office accommodation to support the ongoing operations of Somerset Passenger Solutions at Hinkley Point C.
Health, Safety and Quality
The project was delivered under a comprehensive safety plan incorporating detailed risk assessments and method statements, a traffic management scheme and personal safety procedures.
Daily toolbox talks, together with regular inspections and assessments of equipment and site activities, ensured the building was completed without reportable incident.
The site was protected by temporary fencing throughout the works and clearly displayed warning signage and emergency contact information. Staff competency checks and strict PPE requirements were maintained at all stages of the project.
Upon completion, a comprehensive Operation and Maintenance (O&M) manual was provided to the client. The manual details significant health and safety considerations that must be managed during future maintenance, repair, renovation, alteration or demolition activities.