Demolition of the existing shell commenced, following a comprehensive preconstruction period, which established detailed environmental protection, traffic management and community liaison plans. Due to the limited accessibility of the site and residential surroundings, the mitigation of disruptive activities was paramount.
Groundworks and concrete pad foundations were laid in preparation for the steel structure to take shape over the course of 14 weeks, revealing the impressive, two-storey outline of the building, with generous ceiling heights and a spacious, central atrium.
Concrete pours completed the first floor and innovative roof before the envelope was sealed with a visually striking, glass curtain wall, bounded at either end and centre by architectural brickwork.
The 560m2 walk-on roof supports the M&E installation and associated services and provides access to the roof structures covering the rest of the building.